FLIPPING MANEUVER OF RADIANT SECTION

After the complete vertical assembly of the radiant section of this petrochemical furnace, we performed the flipping maneuver, allowing an easier sea freight.

Project Rotterdam 2018

March 2018

The movement, executed with three heavy lift cranes, took place a few days ago. You can see it in the link.

https://youtu.be/5VNXXS3m0t4

Once in horizontal position, resting on cradles, it was shipped to Rotterdam together with the convection section, breeching, ducts and other minor pieces.